Calculate Your Dispute Timeline

The date s28 notice was served on the Respondent.
The adjudicator can self-extend by up to 10 days; further requires party consent.
From notice to determinationapproximately 10 weeks, ending Thu, 28 Jan 2027

Calculated Procedural Path

Dates assume each step is taken on its deadline. Steps marked “Indicative” reflect CAA's standard workflow rather than a deadline fixed by the Act. Dates do not allow for regional anniversary days (see the note below).

1
Notice of Adjudication Served (s 28)
Trigger Event
Initially served on Respondent
Thu, 19 Nov 2026
2
Request CAA to Nominate Adjudicator (s 33(1)(d))
Action Required
Within 2 to 5 working days of serving notice
Mon, 23 Nov 2026 to Thu, 26 Nov 2026
3
Notice of Willingness Issued (s 35(1))
IndicativePending Willingness
Adjudicator declares independence & willingness within 2 working days of approach
Tue, 01 Dec 2026
4
Notice of Acceptance Served (s 35(2))
IndicativeAppointment Effective
Served on payment of the security deposit. Formally starts the statutory clock.
Fri, 04 Dec 2026
5
Serve Written Adjudication Claim (s 36)
Submission Deadline
Claimant must serve within 5 working days
Fri, 11 Dec 2026
6
Serve Written Response (s 37)
Submission Deadline
Respondent must serve within 5 working days unless extended by agreement of the parties or by the adjudicator (any such extension will delay the following steps)
Fri, 18 Dec 2026
7
Claimant Reply (s 37A)
Optional Rebuttal
Claimant may serve within 5 working days of receiving Response
Thu, 07 Jan 2027
8
Optional Respondent Rejoinder (s 37A(4))
Optional Rejoinder
If permitted, Respondent may serve within 2 working days of receiving Reply
Mon, 11 Jan 2027
9
Adjudicator Determination (s 46)
Binding Decision
Strictly within 20 working days of Response
Thu, 28 Jan 2027

Statutory Timeline Disclaimer

Working days: Saturdays, Sundays, national public holidays (Waitangi Day, Good Friday, Easter Monday, Anzac Day, the Sovereign's Birthday, Te Rā Aro ki a Matariki/Matariki Observance Day, and Labour Day), and the Christmas closure period (24 December to 5 January inclusive) are excluded from the calculation.

Regional anniversary days: the Act also excludes the day observed in the appropriate area as the anniversary of the province (s 5). This calculator does not exclude those days, because they differ from region to region. Where a regional anniversary day falls within a period, that deadline and each later step fall one working day later than shown. Which area is the appropriate area may depend on the circumstances of the adjudication.

This calculator is provided for informational purposes only. The parties should always refer to the Construction Contracts Act 2002, seek their own legal advice, and consult the adjudicator's specific directions when calculating or confirming final timeframes and deadlines under the Act.

Ready to Appoint an Adjudicator?

Explore the CAA List to compare expertise and published rates, or begin your application now.